Project Name
Emergency Rehabilitation and Reconstruction Roads, Bridges and Culverts under Sunamganj and Habiganj Road Division affected by 2022 flood (Habiganj Part).
Start
01/09/2023
End
31/12/2026
Project Type
adb
Amount
9397155000.00
Latest Status
31/12/2026
Job description

Land Acquisition = 71.1851 hectares

Earthworks = 1488447.33 cubic meters

Reconstruction of pavement with hard shoulder (10.30m) = 6.571 km

Widening and strengthening of existing pavement with hard shoulder (5.50m to 10.30m) = 24.864 km

Surfacing (DBS base and wiring course) (10.30m) = 31.968 km

Widening of rigid pavement (10.30m) = 4.136 km

Construction of bus-bay = 4 meters

Development of intersections = 2 Nos

Construction of RCC box culvert = 48.00 meters

Construction of RCC U-drain cum footpath = 10072.00 meters 

Construction of saucer drain = 1400.00 meters 

Geotextile including CC block = 531861.00 sq.m. 

Brick toe wall construction = 66398.00 meters